Hard1 markMultiple Choice
PMP · Question 27 · Task 13: Mentor relevant stakeholders
A project manager is working with a new team member who has strong technical skills but lacks experience with the organization's project management processes. The team member seems overwhelmed by the documentation requirements and process complexity. What should the project manager do to support this team member?
A project manager is working with a new team member who has strong technical skills but lacks experience with the organization's project management processes. The team member seems overwhelmed by the documentation requirements and process complexity. What should the project manager do to support this team member?
Answer options:
A.
Assign the team member to technical tasks only to avoid process complexity
B.
Provide mentoring on organizational processes while leveraging their technical expertise
C.
Pair the team member with someone experienced in organizational processes
D.
Send the team member to formal training on project management processes
How to approach this question
Look for servant leadership approaches that develop team member capabilities while leveraging their existing strengths. Mentoring provides personalized support for integration.
Full Answer
B.Provide mentoring on organizational processes while leveraging their technical expertise✓ Correct
B
Servant leadership focuses on developing team members' capabilities. Mentoring provides personalized support for learning organizational processes while recognizing and leveraging existing technical strengths.
Common mistakes
Limiting the team member's role, delegating mentoring to others, or using generic training instead of personalized support.
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
Expert