PMP · Question 26 · Task 1: Execute project with the urgency required to deliver business value
A project team is using Kanban to manage their workflow. The team notices that work items are spending too much time in the 'In Review' column, creating a bottleneck. The review process involves both technical review by senior developers and business review by product owners. What should the project manager recommend to address this bottleneck?
A project team is using Kanban to manage their workflow. The team notices that work items are spending too much time in the 'In Review' column, creating a bottleneck. The review process involves both technical review by senior developers and business review by product owners. What should the project manager recommend to address this bottleneck?
Answer options:
Increase the work-in-progress (WIP) limit for the 'In Review' column
Assign more people to the review process to increase capacity
Analyze the review process to identify and eliminate inefficiencies or delays
Split the 'In Review' column into separate technical and business review columns
How to approach this question
Full Answer
Common mistakes