PMP · Question 12 · Task 6: Plan and manage schedule
During a project retrospective, the team identifies that they consistently underestimate the effort required for integration testing. Historical data shows their estimates are typically 40% lower than actual effort. The team wants to improve their estimation accuracy for the next iteration. What should the project manager recommend FIRST?
During a project retrospective, the team identifies that they consistently underestimate the effort required for integration testing. Historical data shows their estimates are typically 40% lower than actual effort. The team wants to improve their estimation accuracy for the next iteration. What should the project manager recommend FIRST?
Answer options:
Apply a 40% buffer to all future integration testing estimates
Analyze the root causes of why integration testing consistently takes longer than estimated
Use three-point estimation (optimistic, pessimistic, most likely) for integration testing tasks
Assign integration testing to the most experienced team members to reduce variability
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
Expert