Hard1 markMultiple Choice
Task 6: Plan and manage schedulecontinuous-improvementestimationroot-cause-analysisretrospectives

PMP · Question 12 · Task 6: Plan and manage schedule

During a project retrospective, the team identifies that they consistently underestimate the effort required for integration testing. Historical data shows their estimates are typically 40% lower than actual effort. The team wants to improve their estimation accuracy for the next iteration. What should the project manager recommend FIRST?

Answer options:

A.

Apply a 40% buffer to all future integration testing estimates

B.

Analyze the root causes of why integration testing consistently takes longer than estimated

C.

Use three-point estimation (optimistic, pessimistic, most likely) for integration testing tasks

D.

Assign integration testing to the most experienced team members to reduce variability

How to approach this question

Focus on root cause analysis before implementing solutions. Understanding why estimates are wrong is more valuable than just adjusting the numbers.

Full Answer

B.Analyze the root causes of why integration testing consistently takes longer than estimated✓ Correct
B
Continuous improvement requires understanding root causes. Analyzing why integration testing takes longer than estimated will reveal specific issues that can be addressed, leading to better estimation and potentially improved processes.

Common mistakes

Jumping to solutions like buffers or different estimation techniques without first understanding why the current estimates are inaccurate.

Practice the full PMI PMP Practice Exam 2

100 questions · hints · full answers · grading

More questions from this exam