    PracticePMI PMP®PMI PMP Practice Exam 2Question 81
    Hard1 markMultiple Choice
    Task 1: Execute project with the urgency required to deliver business valuekanbancontext-switchingtask-batchingworkflow-optimization

    PMP · Question 81 · Task 1: Execute project with the urgency required to deliver business value

    A project team is using Kanban to manage workflow, and the project manager notices that work items are consistently taking longer than expected to move through the 'Development' column. Analysis shows that developers are frequently switching between different types of tasks, causing context switching overhead. What should the project manager recommend?

    Answer options:

    A.

    Increase the work-in-progress (WIP) limit for the Development column to allow more parallel work

    B.

    Assign specific developers to specific types of tasks to reduce switching

    C.

    Implement task batching strategies to minimize context switching within the Development column

    D.

    Split the Development column into separate columns for different task types

    How to approach this question

    When context switching is causing delays, look for solutions that reduce switching overhead while maintaining workflow flexibility and team capability.

    Full Answer

    C.Implement task batching strategies to minimize context switching within the Development column✓ Correct
    C
    Context switching creates overhead that reduces productivity. Task batching strategies allow developers to focus on similar work types while maintaining the flexibility and flow benefits of Kanban.

    Common mistakes

    Increasing WIP limits (which worsens context switching), creating rigid specialization, or making structural changes that don't address the switching overhead.
    Question 80All questionsQuestion 82

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →