For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 80
    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefits and valuebusiness-case-updatemarket-changesstakeholder-decision-makingvalue-reassessment

    PMP · Question 80 · Task 2: Evaluate and deliver project benefits and value

    A project manager is working on a project where the business case was based on achieving specific cost savings through process automation. Six months into the project, market conditions have changed and the anticipated cost savings are no longer realistic. However, the automation will still provide other benefits like improved accuracy and faster processing. What should the project manager do?

    Answer options:

    A.

    Continue the project as planned since it will still provide some benefits

    B.

    Update the business case to reflect current conditions and present it to stakeholders for decision

    C.

    Modify the project scope to focus on achieving the original cost savings

    D.

    Terminate the project since the original business case is no longer valid

    How to approach this question

    When fundamental business case assumptions change, update the analysis and engage stakeholders for informed decision-making rather than making unilateral project decisions.

    Full Answer

    B.Update the business case to reflect current conditions and present it to stakeholders for decision✓ Correct
    When market conditions change the fundamental business case, project managers should update the analysis to reflect current conditions and engage stakeholders for informed decision-making about project continuation.

    Common mistakes

    Continuing without reassessment, making unilateral scope or termination decisions, or not engaging stakeholders in business case reevaluation.
    Question 79All questionsQuestion 81

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →