PMP · Question 82 · Task 6: Build a team
A project manager is leading a team that includes both permanent employees and contractors from different companies. The contractors have varying contract terms, different holiday schedules, and some work part-time. Team cohesion is suffering because of these differences in working arrangements and availability. Which TWO strategies should the project manager implement to build team unity?
Answer options:
Establish shared team goals and success metrics that apply to all members regardless of employment status
Create separate communication channels for employees and contractors
Develop flexible meeting and collaboration practices that accommodate different schedules
Require all team members to adopt the same working schedule
Assign contractors to work independently to avoid scheduling conflicts
Focus team building activities only on permanent employees