PMP · Question 70 · Task 7: Plan and manage quality of products/deliverables
A project team is using Scrum and has been consistently delivering working software each sprint. However, the product owner reports that while individual features work correctly, the overall product architecture is becoming fragmented and technical debt is accumulating. What should the project manager recommend?
A project team is using Scrum and has been consistently delivering working software each sprint. However, the product owner reports that while individual features work correctly, the overall product architecture is becoming fragmented and technical debt is accumulating. What should the project manager recommend?
Answer options:
Continue with current practices since the team is delivering working software as required
Dedicate entire sprints to technical debt reduction and architecture improvement
Incorporate architectural planning and technical debt management into regular sprint activities
Switch to a different agile framework that emphasizes architecture planning
How to approach this question
Full Answer
Common mistakes