Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned-value-managementtcpi-calculationcost-performanceproject-forecasting

PMP · Question 91 · Task 5: Plan and manage budget and resources

A project has the following earned value data:<br/><br/>- Budget at Completion (BAC): $800,000<br/>- Earned Value (EV): $480,000<br/>- Actual Cost (AC): $520,000<br/><br/>Assuming current cost performance continues, what is the To Complete Performance Index (TCPI) based on BAC? (Round to two decimal places, enter numbers only)

How to approach this question

Calculate TCPI using the formula: TCPI = (BAC - EV) / (BAC - AC). TCPI = ($800,000 - $480,000) / ($800,000 - $520,000) = $320,000 / $280,000 = 1.143, which rounds to 1.14.

Full Answer

To Complete Performance Index (TCPI) = (BAC - EV) / (BAC - AC) = ($800,000 - $480,000) / ($800,000 - $520,000) = $320,000 / $280,000 = 1.143 ≈ 1.14. This means cost performance must improve to 1.14 to complete within budget.

Common mistakes

Using wrong formula, calculation errors, or confusing TCPI with other EVM indices.

Practice the full PMI PMP Practice Exam 2

100 questions · hints · full answers · grading

More questions from this exam