For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 91
    Hard1 markShort Answer
    Task 5: Plan and manage budget and resourcesearned-value-managementtcpi-calculationcost-performanceproject-forecasting

    PMP · Question 91 · Task 5: Plan and manage budget and resources

    A project has the following earned value data:<br/><br/>- Budget at Completion (BAC): $800,000<br/>- Earned Value (EV): $480,000<br/>- Actual Cost (AC): $520,000<br/><br/>Assuming current cost performance continues, what is the To Complete Performance Index (TCPI) based on BAC? (Round to two decimal places, enter numbers only)

    How to approach this question

    Calculate TCPI using the formula: TCPI = (BAC - EV) / (BAC - AC). TCPI = ($800,000 - $480,000) / ($800,000 - $520,000) = $320,000 / $280,000 = 1.143, which rounds to 1.14.

    Full Answer

    1.14
    To Complete Performance Index (TCPI) = (BAC - EV) / (BAC - AC) = ($800,000 - $480,000) / ($800,000 - $520,000) = $320,000 / $280,000 = 1.143 ≈ 1.14. This means cost performance must improve to 1.14 to complete within budget.

    Common mistakes

    Using wrong formula, calculation errors, or confusing TCPI with other EVM indices.
    Question 90All questionsQuestion 92

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →