PMP · Question 91 · Task 5: Plan and manage budget and resources
A project has the following earned value data:<br/><br/>- Budget at Completion (BAC): $800,000<br/>- Earned Value (EV): $480,000<br/>- Actual Cost (AC): $520,000<br/><br/>Assuming current cost performance continues, what is the To Complete Performance Index (TCPI) based on BAC? (Round to two decimal places, enter numbers only)