PMP · Question 92 · Task 4: Engage stakeholders
A project manager is working with a stakeholder who has high influence but low interest in the project. This stakeholder makes decisions that affect the project but doesn't attend meetings or respond to communications promptly. Their lack of engagement is causing delays in decision-making. What should the project manager do?
Answer options:
Continue sending regular communications and wait for responses
Develop a targeted engagement strategy that addresses the stakeholder's specific interests and communication preferences
Escalate to senior management to compel the stakeholder's participation
Make decisions without the stakeholder's input to avoid delays
100 questions · hints · full answers · grading