For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 36
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksrisk-responserisk-managementoption-evaluationdecision-criteria

    PMP · Question 36 · Task 3: Assess and manage risks

    A project team has identified a risk that a key supplier might not deliver components on time due to their own supply chain issues. The probability is assessed as medium, and the impact would be high, potentially delaying the project by 4-6 weeks. The team has identified three response options: find an alternative supplier, build buffer time into the schedule, or negotiate penalty clauses with the current supplier. What should the project manager do?

    Answer options:

    A.

    Evaluate each response option against cost, feasibility, and effectiveness criteria

    B.

    Implement all three response options to maximize risk mitigation

    C.

    Choose the alternative supplier option since it eliminates the risk entirely

    D.

    Select the schedule buffer option as it's the simplest to implement

    How to approach this question

    Risk response selection requires systematic evaluation of options against multiple criteria rather than choosing based on single factors like simplicity or risk elimination.

    Full Answer

    A.Evaluate each response option against cost, feasibility, and effectiveness criteria✓ Correct
    A
    Effective risk management requires evaluating response options against criteria like cost, feasibility, and effectiveness. This systematic approach ensures the chosen response provides the best value for the project.

    Common mistakes

    Implementing all options without evaluation, choosing based on single criteria like simplicity or risk elimination, or making decisions without systematic comparison.
    Question 35All questionsQuestion 37

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →