Hard1 markMultiple Choice
Task 3: Assess and manage risksrisk-responserisk-managementoption-evaluationdecision-criteria

PMP · Question 36 · Task 3: Assess and manage risks

A project team has identified a risk that a key supplier might not deliver components on time due to their own supply chain issues. The probability is assessed as medium, and the impact would be high, potentially delaying the project by 4-6 weeks. The team has identified three response options: find an alternative supplier, build buffer time into the schedule, or negotiate penalty clauses with the current supplier. What should the project manager do?

Answer options:

A.

Evaluate each response option against cost, feasibility, and effectiveness criteria

B.

Implement all three response options to maximize risk mitigation

C.

Choose the alternative supplier option since it eliminates the risk entirely

D.

Select the schedule buffer option as it's the simplest to implement

How to approach this question

Risk response selection requires systematic evaluation of options against multiple criteria rather than choosing based on single factors like simplicity or risk elimination.

Full Answer

A.Evaluate each response option against cost, feasibility, and effectiveness criteria✓ Correct
Effective risk management requires evaluating response options against criteria like cost, feasibility, and effectiveness. This systematic approach ensures the chosen response provides the best value for the project.

Common mistakes

Implementing all options without evaluation, choosing based on single criteria like simplicity or risk elimination, or making decisions without systematic comparison.

Practice the full PMI PMP Practice Exam 2

100 questions · hints · full answers · grading

More questions from this exam