Hard1 markMultiple Choice
Task 12: Define team ground rulesground-rulesteam-managementconflict-resolutionteam-dynamics

PMP · Question 22 · Task 12: Define team ground rules

A project team has established ground rules including 'all team members will be respectful in communications' and 'decisions will be made collaboratively.' During a heated technical discussion, one team member interrupts others repeatedly and dismisses their ideas without consideration. Other team members are becoming frustrated and disengaged. What should the project manager do?

Answer options:

A.

Ignore the behavior since technical discussions can be passionate and the team member is contributing

B.

Publicly call out the team member's behavior during the meeting to enforce the ground rules

C.

Address the ground rule violation privately with the team member and reinforce expectations

D.

Revise the ground rules to be more specific about acceptable behavior in technical discussions

How to approach this question

Ground rule violations should be addressed promptly but constructively. Private discussion maintains dignity while reinforcing team agreements.

Full Answer

C.Address the ground rule violation privately with the team member and reinforce expectations✓ Correct
C
Effective ground rule management requires prompt but respectful enforcement. Private discussion allows for constructive feedback and behavior correction while maintaining team relationships and psychological safety.

Common mistakes

Ignoring violations, public confrontation, or changing rules instead of enforcing existing ones.