    PracticePMI PMP®PMI PMP Practice Exam 2Question 84
    Hard1 markMultiple Choice
    Task 7: Plan and manage quality of products/deliverablesquality-managementdefect-analysisroot-cause-analysisquality-trends

    PMP · Question 84 · Task 7: Plan and manage quality of products/deliverables

    A project manager is leading a software development project where the development team has been consistently delivering features on time, but the quality assurance team reports that they are finding an increasing number of defects in recent deliverables. The defect trend is upward, and fixing defects is starting to consume significant development time. What should the project manager do FIRST?

    Answer options:

    A.

    Analyze the root causes of the increasing defect trend with both teams

    B.

    Slow down the development pace to allow more time for quality checks

    C.

    Add more quality assurance resources to catch defects earlier

    D.

    Implement additional code review processes

    How to approach this question

    When quality trends are negative, analyze root causes with the affected teams before implementing solutions to ensure interventions address the actual problems.

    Full Answer

    A.Analyze the root causes of the increasing defect trend with both teams✓ Correct
    A
    Quality management requires understanding root causes of problems before implementing solutions. Analyzing the defect trend with both teams reveals the underlying issues that need to be addressed.

    Common mistakes

    Implementing generic solutions without understanding root causes, making assumptions about time pressure, or adding resources without addressing underlying quality issues.
    Question 83All questionsQuestion 85

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →