PMP · Question 30 · Task 6: Plan and manage schedule
A project has the following network diagram with activity durations:<br/><br/>Activity A: 4 days (no predecessors)<br/>Activity B: 6 days (predecessor: A)<br/>Activity C: 3 days (predecessor: A)<br/>Activity D: 5 days (predecessors: B, C)<br/>Activity E: 2 days (predecessor: D)<br/><br/>What is the total project duration in days? (Enter numbers only)
100 questions · hints · full answers · grading