For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 30
    Hard1 markShort Answer
    Task 6: Plan and manage schedulecritical-path-methodnetwork-diagramschedule-calculationproject-duration

    PMP · Question 30 · Task 6: Plan and manage schedule

    A project has the following network diagram with activity durations:<br/><br/>Activity A: 4 days (no predecessors)<br/>Activity B: 6 days (predecessor: A)<br/>Activity C: 3 days (predecessor: A)<br/>Activity D: 5 days (predecessors: B, C)<br/>Activity E: 2 days (predecessor: D)<br/><br/>What is the total project duration in days? (Enter numbers only)

    How to approach this question

    Calculate the critical path by finding the longest path through the network. Path A-B-D-E = 4+6+5+2 = 17 days. Path A-C-D-E = 4+3+5+2 = 14 days. The critical path is 17 days.

    Full Answer

    17
    Critical path method requires calculating all possible paths and selecting the longest. Path 1: A(4) + B(6) + D(5) + E(2) = 17 days. Path 2: A(4) + C(3) + D(5) + E(2) = 14 days. Critical path = 17 days.

    Common mistakes

    Adding all activity durations instead of finding the critical path, or miscalculating the path dependencies.
    Question 29All questionsQuestion 31

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →