PMP · Question 31 · Task 12: Manage project artifacts
A project manager discovers that a key project artifact (the requirements specification) has not been updated in six weeks despite multiple changes being implemented. Team members are working from different versions of the document, leading to confusion and rework. What should the project manager do FIRST?
A project manager discovers that a key project artifact (the requirements specification) has not been updated in six weeks despite multiple changes being implemented. Team members are working from different versions of the document, leading to confusion and rework. What should the project manager do FIRST?
Answer options:
A.
Establish immediate version control and update the requirements specification with all recent changes
B.
Investigate who was responsible for maintaining the requirements specification
C.
Schedule a meeting with all stakeholders to review the requirements
D.
Implement a new artifact management process to prevent future issues
How to approach this question
When project artifacts are causing active confusion and rework, immediate correction and control must come before investigation or process improvement.
Full Answer
A.Establish immediate version control and update the requirements specification with all recent changes✓ Correct
A
Project artifact management requires immediate action when outdated information is causing active problems. Establishing version control and updating the artifact stops further confusion and rework.
Common mistakes
Focusing on accountability or process improvement before addressing the immediate problem causing team confusion and rework.
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
Expert