    PracticePMI PMP®PMI PMP Practice Exam 2Question 43
    Hard1 markMultiple Choice
    Task 11: Engage and support virtual teamsvirtual-teamsteam-engagementcollaboration-toolsrelationship-building

    PMP · Question 43 · Task 11: Engage and support virtual teams

    A project manager is working with a virtual team spread across multiple time zones. Team members report feeling disconnected from each other and the project, leading to decreased collaboration and motivation. The project requires high levels of coordination and knowledge sharing. Which TWO strategies should the project manager implement to improve virtual team engagement?

    Answer options:

    A.

    Schedule all meetings during overlapping business hours for all time zones

    B.

    Create regular informal interaction opportunities like virtual coffee chats or team check-ins

    C.

    Require all team members to be online during core business hours

    D.

    Reduce the frequency of team meetings to minimize scheduling conflicts

    E.

    Implement collaborative tools and platforms that support asynchronous knowledge sharing

    F.

    Assign team members to work in pairs within the same time zone

    How to approach this question

    Look for strategies that build relationships (informal interactions) and enable effective collaboration across time zones (asynchronous tools) rather than forcing synchronous work.

    Full Answer

    Virtual team engagement requires both relationship building (informal interactions) and effective collaboration tools (asynchronous platforms). These strategies address the unique challenges of distributed teams.

    Common mistakes

    Trying to force synchronous work across time zones, reducing communication, or creating silos instead of building team cohesion.
    Question 42All questionsQuestion 44

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →