Hard1 markMultiple Choice
Task 4: Support organizational changedigital-transformationchange-managementuser-adoptionbusiness-value

PMP · Question 42 · Task 4: Support organizational change

A project manager is leading a digital transformation project that will change core business processes. Early user feedback indicates resistance to the new system, with concerns about job security and increased complexity. The technical implementation is proceeding smoothly, but user adoption metrics are below expectations. What should the project manager focus on?

Answer options:

A.

Continue with technical implementation since that is proceeding well

B.

Delay the project until user concerns are fully resolved

C.

Implement change management strategies to address user concerns and improve adoption

D.

Simplify the technical solution to reduce complexity concerns

How to approach this question

Digital transformation projects require both technical implementation and change management. User adoption is critical for realizing business value.

Full Answer

C.Implement change management strategies to address user concerns and improve adoption✓ Correct
C
Digital transformation projects succeed through both technical implementation and user adoption. Change management strategies are essential to address resistance and ensure the transformation delivers intended business value.

Common mistakes

Focusing only on technical implementation, delaying unnecessarily, or making technical changes without addressing underlying change resistance.