For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 44
    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefits and valuebusiness-valuestakeholder-engagementmarket-changesvalue-optimization

    PMP · Question 44 · Task 2: Evaluate and deliver project benefits and value

    A project manager discovers that the project's current trajectory will deliver the technical requirements but may not achieve the expected business benefits due to changes in market conditions since project initiation. The sponsor is focused on completing the technical deliverables as planned. What should the project manager do?

    Answer options:

    A.

    Continue with the planned technical deliverables since they meet the original requirements

    B.

    Present the business value analysis to the sponsor and recommend adjustments to maximize benefits

    C.

    Complete the technical deliverables and document the business value concerns for future reference

    D.

    Modify the technical deliverables without sponsor approval to better align with current market conditions

    How to approach this question

    When business value is at risk due to changing conditions, the PM should engage stakeholders with analysis and recommendations rather than just delivering technical requirements.

    Full Answer

    B.Present the business value analysis to the sponsor and recommend adjustments to maximize benefits✓ Correct
    Project managers are responsible for delivering business value, not just technical requirements. When market changes threaten value realization, stakeholder engagement with analysis and recommendations is essential.

    Common mistakes

    Focusing only on technical delivery, documenting concerns without action, or making unilateral changes without stakeholder engagement.
    Question 43All questionsQuestion 45

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →