PMP · Question 33 · Task 1: Plan and manage project compliance
A project manager is working on a government contract that requires specific security clearances for team members. Two weeks into the project, one team member's security clearance is revoked due to personal issues unrelated to work performance. This team member was responsible for 25% of the critical path activities. What should the project manager do FIRST?
Answer options:
Immediately remove the team member and redistribute their work to other cleared team members
Request an expedited security clearance review for the team member
Assess the impact on project schedule and identify options for replacing the team member or redistributing work
Escalate to the client to request a waiver for the security clearance requirement
100 questions · hints · full answers · grading