PMP · Question 10 · Task 10: Manage project changes
A key stakeholder requests a significant feature addition during the execution phase of a predictive project. The change would add substantial business value but would impact the timeline by 6 weeks and increase the budget by 15%. The stakeholder has significant influence and is pressuring for immediate implementation. What should the project manager do FIRST?
A key stakeholder requests a significant feature addition during the execution phase of a predictive project. The change would add substantial business value but would impact the timeline by 6 weeks and increase the budget by 15%. The stakeholder has significant influence and is pressuring for immediate implementation. What should the project manager do FIRST?
Answer options:
Implement the change immediately to satisfy the key stakeholder and maintain the relationship
Reject the change to protect the project baseline and schedule
Assess the impact on scope, schedule, and cost, then submit to the change control board
Negotiate with the stakeholder to defer the change to a future phase or project
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
Expert