    PracticePMI PMP®PMI PMP Practice Exam 2Question 09
    Hard1 markMultiple Choice
    Task 7: Address and remove impediments, obstacles, and blockers for the teamservant-leadershipimpediment-removalteam-supportcollaboration

    PMP · Question 09 · Task 7: Address and remove impediments, obstacles, and blockers for the team

    An agile development team reports during the daily stand-up that they cannot proceed with testing the core authentication module because the test environment is not available. The infrastructure team says it will take three more days to set up the environment, but this will block 60% of the current sprint work. The sprint ends in four days. What should the project manager do FIRST?

    Answer options:

    A.

    Add the delay to the risk register and inform the sponsor about the potential sprint failure

    B.

    Work with the infrastructure team to explore options for expediting the environment or finding alternatives

    C.

    Ask the development team to work on other user stories while waiting for the environment

    D.

    Escalate to senior management to prioritize the infrastructure work immediately

    How to approach this question

    Look for servant leadership actions that actively work to remove blockers. The PM should collaborate with other teams to find immediate solutions rather than just documenting or escalating.

    Full Answer

    B.Work with the infrastructure team to explore options for expediting the environment or finding alternatives✓ Correct
    Servant leaders actively work to remove impediments for their teams. This means collaborating with the infrastructure team to explore expedited solutions or alternatives rather than just documenting the issue or escalating.

    Common mistakes

    Choosing passive responses like documentation or premature escalation instead of active collaboration to remove blockers.
    Question 08All questionsQuestion 10

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →