PMP · Question 20 · Task 2: Lead a team
A project manager is leading a team that includes both experienced senior developers and recent graduates. The senior developers prefer to work independently and make technical decisions autonomously, while the junior developers need more guidance and support. The project requires both groups to collaborate effectively. Which TWO leadership approaches should the project manager use?
A project manager is leading a team that includes both experienced senior developers and recent graduates. The senior developers prefer to work independently and make technical decisions autonomously, while the junior developers need more guidance and support. The project requires both groups to collaborate effectively. Which TWO leadership approaches should the project manager use?
Answer options:
Apply situational leadership by adapting leadership style based on individual team member needs
Use a consistent directive leadership style to ensure all team members follow the same processes
Implement a democratic leadership approach where all decisions are made by team consensus
Empower senior developers with decision-making authority while providing coaching support to junior developers
Separate the senior and junior developers into different workstreams to avoid conflicts
Assign all technical decisions to senior developers and limit junior developers to implementation tasks
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
Expert