PMP · Question 64 · Task 5: Ensure team members/stakeholders are adequately trained
A project team has been working effectively together for six months. A new organizational policy requires all team members to complete additional compliance training that will take each person away from project work for two full days. The training is mandatory and cannot be postponed. The project is in a critical phase with tight deadlines. What should the project manager do?
A project team has been working effectively together for six months. A new organizational policy requires all team members to complete additional compliance training that will take each person away from project work for two full days. The training is mandatory and cannot be postponed. The project is in a critical phase with tight deadlines. What should the project manager do?
Answer options:
Request an exemption from the training requirement due to project criticality
Adjust the project schedule to accommodate the training while minimizing impact on critical deliverables
Have team members complete the training during their personal time
Delay the training until after the critical project phase is complete
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading