    PracticePMI PMP®PMI PMP Practice Exam 2Question 64
    Hard1 markMultiple Choice
    Task 5: Ensure team members/stakeholders are adequately trainedcompliance-trainingmandatory-requirementsschedule-adjustmentorganizational-policy

    PMP · Question 64 · Task 5: Ensure team members/stakeholders are adequately trained

    A project team has been working effectively together for six months. A new organizational policy requires all team members to complete additional compliance training that will take each person away from project work for two full days. The training is mandatory and cannot be postponed. The project is in a critical phase with tight deadlines. What should the project manager do?

    Answer options:

    A.

    Request an exemption from the training requirement due to project criticality

    B.

    Adjust the project schedule to accommodate the training while minimizing impact on critical deliverables

    C.

    Have team members complete the training during their personal time

    D.

    Delay the training until after the critical project phase is complete

    How to approach this question

    When mandatory organizational requirements conflict with project schedules, adjust the project to accommodate the requirements rather than trying to avoid them.

    Full Answer

    B.Adjust the project schedule to accommodate the training while minimizing impact on critical deliverables✓ Correct
    B
    Mandatory organizational requirements must be accommodated in project planning. Proactive schedule adjustment minimizes impact while ensuring compliance with organizational policies.

    Common mistakes

    Trying to avoid mandatory requirements, asking team members to use personal time, or delaying compliance activities for project convenience.
    Question 63All questionsQuestion 65

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →