    PracticePMI PMP®PMI PMP Practice Exam 2Question 38
    Hard1 markMultiple Choice
    Task 17: Plan and manage project/phase closure or transitionsphase-transitionentry-criteriaquality-gatesteam-collaboration

    PMP · Question 38 · Task 17: Plan and manage project/phase closure or transitions

    A project is transitioning from the development phase to the testing phase. The development team has completed their work, but the testing team reports that the deliverables don't meet the entry criteria for testing due to incomplete documentation and missing test data. The development team is already assigned to a new project. What should the project manager do?

    Answer options:

    A.

    Ask the testing team to proceed with testing using available information

    B.

    Work with both teams to resolve the entry criteria gaps before proceeding with the transition

    C.

    Escalate to management to get the development team reassigned to complete the missing work

    D.

    Update the entry criteria to match what the development team has delivered

    How to approach this question

    Phase transitions require meeting defined criteria. Work collaboratively to resolve gaps rather than lowering standards or forcing transitions.

    Full Answer

    B.Work with both teams to resolve the entry criteria gaps before proceeding with the transition✓ Correct
    Effective project phase management requires meeting transition criteria to ensure quality and effectiveness. Collaborative problem-solving between teams is the first approach to resolve gaps.

    Common mistakes

    Forcing transitions without meeting criteria, lowering standards to match deliverables, or escalating before attempting collaborative resolution.
    Question 37All questionsQuestion 39

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →