PMP · Question 38 · Task 17: Plan and manage project/phase closure or transitions
A project is transitioning from the development phase to the testing phase. The development team has completed their work, but the testing team reports that the deliverables don't meet the entry criteria for testing due to incomplete documentation and missing test data. The development team is already assigned to a new project. What should the project manager do?
A project is transitioning from the development phase to the testing phase. The development team has completed their work, but the testing team reports that the deliverables don't meet the entry criteria for testing due to incomplete documentation and missing test data. The development team is already assigned to a new project. What should the project manager do?
Answer options:
Ask the testing team to proceed with testing using available information
Work with both teams to resolve the entry criteria gaps before proceeding with the transition
Escalate to management to get the development team reassigned to complete the missing work
Update the entry criteria to match what the development team has delivered
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
Expert