Hard1 markMultiple Choice
PMP · Question 39 · Task 3: Support team performance
A project manager notices that team productivity has decreased significantly over the past two weeks. Team members seem disengaged during meetings and are not collaborating as effectively as before. The project is technically on track, but the team dynamics have clearly changed. What should the project manager do FIRST?
A project manager notices that team productivity has decreased significantly over the past two weeks. Team members seem disengaged during meetings and are not collaborating as effectively as before. The project is technically on track, but the team dynamics have clearly changed. What should the project manager do FIRST?
Answer options:
A.
Conduct one-on-one conversations with team members to understand what has changed
B.
Organize a team-building activity to improve morale and collaboration
C.
Continue monitoring since the project is technically on track
D.
Implement new collaboration tools to improve team interaction
How to approach this question
When team dynamics change significantly, understanding the root cause through direct communication is essential before implementing solutions.
Full Answer
A.Conduct one-on-one conversations with team members to understand what has changed✓ Correct
A
Effective team leadership requires understanding the root causes of team dynamic changes. One-on-one conversations provide safe spaces for team members to share concerns and insights.
Common mistakes
Implementing solutions without understanding the problem, ignoring team dynamics because technical progress continues, or assuming generic team-building will solve specific issues.
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard