Hard1 markMultiple Choice
PMP · Question 100 · Task 10: Build shared understanding
In a multi-cultural project team, a misunderstanding regarding the definition of 'Done' has led to quality issues. The team members from one region believe testing is a separate phase, while others believe it is part of development. What should the project manager do to build a shared understanding?
In a multi-cultural project team, a misunderstanding regarding the definition of 'Done' has led to quality issues. The team members from one region believe testing is a separate phase, while others believe it is part of development. What should the project manager do to build a shared understanding?
Answer options:
A.
Update the project management plan to define 'Done' and email it to the team.
B.
Assign the QA lead to define the standard and enforce it.
C.
Facilitate a workshop with the entire team to co-create a Definition of Done (DoD).
D.
Adopt the definition used by the team members with the most experience.
How to approach this question
Look for the option that involves the team in the solution (collaborative/participatory).
Full Answer
C.Facilitate a workshop with the entire team to co-create a Definition of Done (DoD).✓ Correct
C
Workshops allow for dialogue, clarification of cultural/process differences, and agreement on a single standard.
Common mistakes
Relying on documents (A) or authority (B) to solve a cultural/understanding gap.
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
Expert