For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 61
    Hard1 markMultiple Choice
    Task 3: Assess and manage riskstechnical-debtimpact-assessmentintegration-risksunexpected-discoveries

    PMP · Question 61 · Task 3: Assess and manage risks

    A project manager is working on a complex integration project involving multiple legacy systems. The technical team reports that they have discovered significant technical debt in one of the legacy systems that will require additional work to address before integration can proceed safely. This was not anticipated in the original planning. What should the project manager do FIRST?

    Answer options:

    A.

    Assess the impact of the technical debt on project scope, schedule, and risk profile

    B.

    Proceed with integration and address technical debt issues as they arise

    C.

    Immediately begin work to resolve the technical debt

    D.

    Escalate the technical debt discovery to senior management

    How to approach this question

    When unexpected technical issues are discovered, assess the full impact first to enable informed decision-making about response options.

    Full Answer

    A.Assess the impact of the technical debt on project scope, schedule, and risk profile✓ Correct
    A
    Unexpected technical discoveries require thorough impact assessment to understand implications for scope, schedule, cost, and risk. This information enables informed stakeholder decision-making about response approaches.

    Common mistakes

    Proceeding without addressing known risks, starting remediation work without approval, or escalating without providing complete impact information.
    Question 60All questionsQuestion 62

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →