For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 58
    Hard1 markMultiple Choice
    Task 2: Manage communicationsstakeholder-balancereporting-efficiencycollaborative-solutionsproductivity-optimization

    PMP · Question 58 · Task 2: Manage communications

    A project manager is leading a software development project where the client has requested detailed progress reports every week. The development team feels that preparing these reports takes significant time away from development work and reduces their productivity. The client insists the reports are necessary for their internal stakeholder management. How should the project manager address this situation?

    Answer options:

    A.

    Eliminate the weekly reports to maximize development team productivity

    B.

    Work with both parties to identify the essential information needed and streamline the reporting process

    C.

    Continue with the current reporting requirements since the client is paying for the project

    D.

    Assign a dedicated person to handle all reporting activities

    How to approach this question

    When stakeholders have conflicting needs, look for collaborative solutions that address the underlying requirements of both parties.

    Full Answer

    B.Work with both parties to identify the essential information needed and streamline the reporting process✓ Correct
    Effective stakeholder management involves finding solutions that meet underlying needs. Streamlining reporting can provide necessary client information while reducing the productivity impact on the development team.

    Common mistakes

    Choosing one stakeholder's needs over another's, adding resources without addressing efficiency, or not exploring collaborative optimization options.
    Question 57All questionsQuestion 59

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →