    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceconfidentiality-breachinformation-securityrisk-containmentimmediate-response

    PMP · Question 57 · Task 1: Plan and manage project compliance

    A project manager discovers that a team member has been sharing confidential project information with colleagues outside the project team. The information shared includes competitive intelligence and strategic plans that could harm the organization if disclosed further. The team member claims they didn't realize the information was confidential. What should the project manager do FIRST?

    Answer options:

    A.

    Immediately contain the information disclosure and assess the potential impact

    B.

    Provide training to the team member about confidentiality requirements

    C.

    Report the incident to HR for disciplinary action

    D.

    Document the incident and continue monitoring the team member's behavior

    How to approach this question

    Confidentiality breaches require immediate containment and impact assessment before training, disciplinary action, or documentation.

    Full Answer

    A.Immediately contain the information disclosure and assess the potential impact✓ Correct
    A
    Confidentiality breaches pose immediate risks to the organization. Containment prevents further disclosure while impact assessment determines the extent of potential damage and necessary responses.

    Common mistakes

    Focusing on training or discipline before containment, or treating documentation as the immediate priority over damage control.
    Question 56All questionsQuestion 58

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →