Hard1 markMultiple Choice
Task 10: Manage project changesagile-principlessprint-commitmentproduct-owner-educationchange-protocols
PMP · Question 48 · Task 10: Manage project changes
A project manager is working on a software development project using an agile approach. The product owner frequently changes priorities during sprints, causing the team to stop work on some user stories and start others. This is affecting team morale and sprint predictability. What should the project manager do?
A project manager is working on a software development project using an agile approach. The product owner frequently changes priorities during sprints, causing the team to stop work on some user stories and start others. This is affecting team morale and sprint predictability. What should the project manager do?
Answer options:
A.
Allow the changes since agile values responding to change over following a plan
B.
Refuse all mid-sprint changes to protect team productivity
C.
Educate the product owner about sprint commitment and establish clear change protocols
D.
Switch to a more flexible agile framework that accommodates frequent changes
How to approach this question
Mid-sprint changes violate agile principles about sprint commitment. Address this through education and establishing proper change protocols.
Full Answer
C.Educate the product owner about sprint commitment and establish clear change protocols✓ Correct
C
Agile frameworks include sprint commitment principles that protect team focus and predictability. Mid-sprint changes should be exceptional, requiring education about agile principles and clear protocols.
Common mistakes
Allowing unlimited mid-sprint changes, rigidly refusing all changes, or changing frameworks instead of addressing the protocol issue.
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
Expert