PMP · Question 47 · Task 10: Manage project changes
A project manager receives a change request that would add significant value to the project but would require extending the timeline by 3 months and increasing the budget by 20%. The change aligns with organizational strategy but wasn't anticipated during initial planning. The project is currently on schedule and within budget. What should the project manager do FIRST?
Answer options:
Conduct a comprehensive impact analysis including benefits, costs, risks, and alternatives
Reject the change to protect the current project baseline
Accept the change since it aligns with organizational strategy
Negotiate with the requestor to reduce the scope of the change