For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 73
    Hard1 markMultiple Choice
    Task 11: Plan and manage procurementvendor-riskfinancial-assessmentrisk-evaluationvendor-management

    PMP · Question 73 · Task 11: Plan and manage procurement

    A project manager discovers that a critical vendor has been experiencing financial difficulties and may not be able to complete their contracted deliverables. The vendor represents 40% of the project scope and finding an alternative would require 6-8 weeks. The project is currently on schedule with 3 months remaining. What should the project manager do FIRST?

    Answer options:

    A.

    Assess the vendor's actual financial status and likelihood of completing deliverables

    B.

    Immediately begin searching for alternative vendors to replace the current one

    C.

    Negotiate payment terms to help the vendor complete the work

    D.

    Escalate to senior management for guidance on vendor replacement

    How to approach this question

    When vendor risks are identified, assess the actual situation first to determine the real risk level before implementing response strategies.

    Full Answer

    A.Assess the vendor's actual financial status and likelihood of completing deliverables✓ Correct
    A
    Vendor risk management requires accurate assessment of the actual situation before implementing response strategies. Understanding the real risk level enables appropriate and proportionate responses.

    Common mistakes

    Taking immediate action based on rumors, starting costly alternatives before confirming risks, or escalating without providing complete assessment information.
    Question 72All questionsQuestion 74

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →