PMP · Question 74 · Task 10: Build shared understanding
A project manager is leading a cross-cultural team with members from high-context and low-context cultures. During team meetings, misunderstandings frequently occur because high-context team members communicate indirectly while low-context members prefer explicit, direct communication. This is affecting team collaboration and decision-making. What should the project manager do?
A project manager is leading a cross-cultural team with members from high-context and low-context cultures. During team meetings, misunderstandings frequently occur because high-context team members communicate indirectly while low-context members prefer explicit, direct communication. This is affecting team collaboration and decision-making. What should the project manager do?
Answer options:
Require all team members to use direct, explicit communication styles
Facilitate cultural awareness training and establish communication protocols that bridge different styles
Separate team members by communication style to avoid misunderstandings
Act as a translator between different communication styles during meetings
How to approach this question