For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 75
    Hard1 markMultiple Choice
    Task 3: Evaluate and address external business environment changes for impact on scoperegulatory-compliancerequirement-changesimpact-assessmentstakeholder-communication

    PMP · Question 75 · Task 3: Evaluate and address external business environment changes for impact on scope

    A project manager is working on a regulatory compliance project where the regulatory agency has updated their requirements midway through the project. The new requirements don't invalidate previous work but add additional compliance steps that will extend the timeline by 4-6 weeks. The project sponsor is concerned about the delay. What should the project manager do?

    Answer options:

    A.

    Continue with the original requirements since the work is already in progress

    B.

    Assess the impact of the new requirements and present options to the sponsor

    C.

    Negotiate with the regulatory agency to delay implementation of the new requirements

    D.

    Implement the new requirements without informing the sponsor to avoid concerns

    How to approach this question

    When regulatory requirements change, assess the impact and engage stakeholders with options rather than ignoring requirements or making unilateral decisions.

    Full Answer

    B.Assess the impact of the new requirements and present options to the sponsor✓ Correct
    B
    Regulatory compliance is mandatory, but stakeholders need to understand the impact of changes. Assessing impact and presenting options enables informed decision-making about how to address new requirements.

    Common mistakes

    Ignoring regulatory changes, trying to negotiate non-negotiable requirements, or implementing changes without stakeholder engagement.
    Question 74All questionsQuestion 76

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →