For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 76
    Hard1 markShort Answer
    Task 6: Plan and manage scheduleearned-value-managementschedule-performancespi-calculationproject-metrics

    PMP · Question 76 · Task 6: Plan and manage schedule

    A project has the following earned value data at the end of month 8:<br/><br/>- Planned Value (PV): $400,000<br/>- Earned Value (EV): $350,000<br/>- Actual Cost (AC): $380,000<br/><br/>What is the Schedule Performance Index (SPI)? (Round to two decimal places, enter numbers only)

    How to approach this question

    Calculate SPI using the formula: SPI = EV / PV. SPI = $350,000 / $400,000 = 0.875, which rounds to 0.88.

    Full Answer

    Schedule Performance Index (SPI) = Earned Value / Planned Value = $350,000 / $400,000 = 0.875 ≈ 0.88. An SPI less than 1.0 indicates the project is behind schedule.

    Common mistakes

    Using the wrong formula (confusing with CPI), calculation errors, or incorrect rounding.
    Question 75All questionsQuestion 77

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →