Hard1 markShort Answer
Task 6: Plan and manage scheduleearned-value-managementschedule-performancespi-calculationproject-metrics

PMP · Question 76 · Task 6: Plan and manage schedule

A project has the following earned value data at the end of month 8:<br/><br/>- Planned Value (PV): $400,000<br/>- Earned Value (EV): $350,000<br/>- Actual Cost (AC): $380,000<br/><br/>What is the Schedule Performance Index (SPI)? (Round to two decimal places, enter numbers only)

How to approach this question

Calculate SPI using the formula: SPI = EV / PV. SPI = $350,000 / $400,000 = 0.875, which rounds to 0.88.

Full Answer

0.88
Schedule Performance Index (SPI) = Earned Value / Planned Value = $350,000 / $400,000 = 0.875 ≈ 0.88. An SPI less than 1.0 indicates the project is behind schedule.

Common mistakes

Using the wrong formula (confusing with CPI), calculation errors, or incorrect rounding.

Practice the full PMI PMP Practice Exam 2

100 questions · hints · full answers · grading

More questions from this exam