A project has the following earned value data at the end of month 8:<br/><br/>- Planned Value (PV): $400,000<br/>- Earned Value (EV): $350,000<br/>- Actual Cost (AC): $380,000<br/><br/>What is the Schedule Performance Index (SPI)? (Round to two decimal places, enter numbers only)
A project has the following earned value data at the end of month 8:<br/><br/>- Planned Value (PV): $400,000<br/>- Earned Value (EV): $350,000<br/>- Actual Cost (AC): $380,000<br/><br/>What is the Schedule Performance Index (SPI)? (Round to two decimal places, enter numbers only)
How to approach this question
Calculate SPI using the formula: SPI = EV / PV. SPI = $350,000 / $400,000 = 0.875, which rounds to 0.88.
Full Answer
0.88
Schedule Performance Index (SPI) = Earned Value / Planned Value = $350,000 / $400,000 = 0.875 ≈ 0.88. An SPI less than 1.0 indicates the project is behind schedule.
Common mistakes
Using the wrong formula (confusing with CPI), calculation errors, or incorrect rounding.
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
Expert