PMP · Question 72 · Task 4: Support organizational change
A project manager is working on a project that involves implementing new technology across multiple business units. Each business unit has different readiness levels for the technology adoption, with some units eager to proceed and others resistant to change. The project timeline assumes uniform rollout across all units. What should the project manager do?
A project manager is working on a project that involves implementing new technology across multiple business units. Each business unit has different readiness levels for the technology adoption, with some units eager to proceed and others resistant to change. The project timeline assumes uniform rollout across all units. What should the project manager do?
Answer options:
Proceed with uniform rollout as planned to maintain project schedule
Focus only on the eager units and delay implementation for resistant units
Develop differentiated change management approaches based on each unit's readiness level
Mandate adoption across all units with strict compliance deadlines
How to approach this question
Full Answer
Common mistakes