PMP · Question 07 · Task 7: Plan and manage quality of products/deliverables
A software project team has been tracking defects found during testing sprints. The data shows:<br/><br/>| Sprint | Defects Found | Defects Fixed | Remaining Defects |<br/>|--------|---------------|---------------|-------------------|<br/>| 1 | 23 | 20 | 3 |<br/>| 2 | 31 | 28 | 6 |<br/>| 3 | 28 | 25 | 9 |<br/>| 4 | 35 | 30 | 14 |<br/>| 5 | 40 | 32 | 22 |<br/><br/>What does this trend MOST likely indicate about the project?
A software project team has been tracking defects found during testing sprints. The data shows:<br/><br/>| Sprint | Defects Found | Defects Fixed | Remaining Defects |<br/>|--------|---------------|---------------|-------------------|<br/>| 1 | 23 | 20 | 3 |<br/>| 2 | 31 | 28 | 6 |<br/>| 3 | 28 | 25 | 9 |<br/>| 4 | 35 | 30 | 14 |<br/>| 5 | 40 | 32 | 22 |<br/><br/>What does this trend MOST likely indicate about the project?
Answer options:
The team's testing effectiveness is improving as they find more defects each sprint
Technical debt is accumulating faster than it's being resolved, indicating a quality issue
The increasing defect count shows the product is becoming more complex, which is normal
The team should reduce testing efforts in the next sprint to focus on fixing existing defects
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
Expert