PMP · Question 86 · Task 11: Plan and manage procurement
A project manager is working on a project that involves multiple external vendors. One vendor has consistently delivered high-quality work but is frequently late with deliverables, causing delays for other vendors who depend on their output. The vendor claims that the project requirements are more complex than originally understood. What should the project manager do?
Answer options:
Replace the vendor with one that can meet the delivery timelines
Accept the delays since the vendor produces high-quality work
Work with the vendor to understand the complexity issues and develop solutions
Impose penalty clauses for future late deliveries