    PracticePMI PMP®PMI PMP Practice Exam 2Question 68
    Hard1 markMultiple Choice
    Task 8: Negotiate project agreementsmatrix-organizationincentive-alignmentfunctional-managerscross-departmental-teams

    PMP · Question 68 · Task 8: Negotiate project agreements

    A project manager is leading a team that includes members from different functional departments. Each department has different performance metrics and incentive structures. Team members are prioritizing work that benefits their departmental metrics over project objectives. This is creating conflicts and reducing overall project effectiveness. What should the project manager do?

    Answer options:

    A.

    Report the issue to senior management and request unified performance metrics for all team members

    B.

    Work with functional managers to align departmental incentives with project objectives

    C.

    Create project-specific incentives that override departmental metrics

    D.

    Focus team members on project objectives and ignore departmental metrics

    How to approach this question

    When departmental incentives conflict with project objectives, work with functional managers to create alignment rather than trying to override existing systems.

    Full Answer

    B.Work with functional managers to align departmental incentives with project objectives✓ Correct
    B
    Matrix organizations require alignment between departmental and project objectives. Working with functional managers to align incentives addresses the root cause of conflicting priorities.

    Common mistakes

    Trying to override departmental systems, ignoring incentive structures, or escalating without attempting collaborative alignment.
    Question 67All questionsQuestion 69

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard