    PracticePMI PMP®PMI PMP Practice Exam 2Question 66
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transfer for project continuityknowledge-transferteam-member-departurecritical-knowledgeproject-continuity

    PMP · Question 66 · Task 16: Ensure knowledge transfer for project continuity

    A project manager discovers that a key team member has been offered a promotion to another department and will be leaving the project in two weeks. This team member has critical knowledge about system integrations that hasn't been fully documented. The project is 70% complete and the integration work is scheduled for the next phase. What should the project manager do FIRST?

    Answer options:

    A.

    Immediately begin knowledge transfer activities to capture the team member's critical knowledge

    B.

    Negotiate with the other department to delay the team member's transfer

    C.

    Find a replacement team member with similar integration experience

    D.

    Accelerate the integration work to complete it before the team member leaves

    How to approach this question

    When key team members with critical knowledge are leaving, immediate knowledge transfer is the highest priority to prevent knowledge loss.

    Full Answer

    A.Immediately begin knowledge transfer activities to capture the team member's critical knowledge✓ Correct
    A
    Knowledge transfer is time-sensitive and critical for project continuity. When key team members leave, capturing their knowledge immediately prevents project risks from knowledge loss.

    Common mistakes

    Trying to delay departures, focusing on replacements before knowledge capture, or accelerating work instead of ensuring knowledge transfer.
    Question 65All questionsQuestion 67

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard