For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 5Question 21
    Hard1 markMultiple Choice
    Task 5: Plan and manage budget and resourcesbudget managementearned value managementcost projectionstakeholder communication

    PMP · Question 21 · Task 5: Plan and manage budget and resources

    A project manager is reviewing the budget performance and notices that the project is currently over budget due to higher than expected resource costs. The sponsor is concerned about cost overruns and wants to understand the future budget implications. The project is 60% complete with a CPI of 0.85. What should the project manager do FIRST?

    Answer options:

    A.

    Calculate the Estimate at Completion (EAC) to project the final project cost based on current performance

    B.

    Implement immediate cost reduction measures to bring the project back on budget

    C.

    Request additional budget from the sponsor to cover the cost overruns

    D.

    Analyze the root causes of the higher resource costs to prevent future overruns

    How to approach this question

    When sponsors are concerned about budget implications, provide data-driven projections first to enable informed decision-making before implementing solutions.

    Full Answer

    A.Calculate the Estimate at Completion (EAC) to project the final project cost based on current performance✓ Correct
    A
    EAC calculations provide stakeholders with data-driven projections of final project costs based on current performance, enabling informed decisions about budget management strategies.

    Common mistakes

    Students often choose immediate cost reduction (B) or budget requests (C), missing the need to first provide analytical projections that enable informed stakeholder decision-making.
    Question 20All questionsQuestion 22

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →