PMP · Question 20 · Task 4: Engage stakeholders
A project manager has completed a stakeholder analysis and identified that the Chief Financial Officer has high power and high interest in the project, while the IT Security team has low power but high interest. The Marketing department has high power but low interest. According to stakeholder engagement best practices, how should the project manager approach the IT Security team?
A project manager has completed a stakeholder analysis and identified that the Chief Financial Officer has high power and high interest in the project, while the IT Security team has low power but high interest. The Marketing department has high power but low interest. According to stakeholder engagement best practices, how should the project manager approach the IT Security team?
Answer options:
Manage closely with frequent detailed updates and active involvement in decisions
Keep informed with regular updates and involve in relevant technical discussions
Monitor with minimal communication since they have low organizational power
Keep satisfied with high-level updates to maintain their support
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
Expert