PMP · Question 22 · Task 6: Plan and manage schedule
A project has the following activity durations and dependencies:<br/>- Activity A: 4 days (no predecessors)<br/>- Activity B: 6 days (predecessor: A)<br/>- Activity C: 3 days (predecessor: A)<br/>- Activity D: 5 days (predecessors: B, C)<br/>- Activity E: 2 days (predecessor: D)<br/><br/>What is the total project duration in days? (Enter numbers only)
94 questions · hints · full answers · grading