Hard1 markShort Answer
Task 6: Plan and manage schedulecritical path methodproject schedulingnetwork analysisactivity dependencies

PMP · Question 22 · Task 6: Plan and manage schedule

A project has the following activity durations and dependencies:<br/>- Activity A: 4 days (no predecessors)<br/>- Activity B: 6 days (predecessor: A)<br/>- Activity C: 3 days (predecessor: A)<br/>- Activity D: 5 days (predecessors: B, C)<br/>- Activity E: 2 days (predecessor: D)<br/><br/>What is the total project duration in days? (Enter numbers only)

How to approach this question

Calculate the critical path by finding the longest path through the network. Add up the durations of activities on the critical path.

Full Answer

Critical path: A(4) → B(6) → D(5) → E(2) = 17 days. Path A-C-D-E = 4+3+5+2 = 14 days, which is shorter.

Common mistakes

Students often add all activity durations (20 days) or calculate the A-C-D-E path (14 days) instead of finding the critical path A-B-D-E (17 days).

Practice the full PMI PMP Practice Exam 5

94 questions · hints · full answers · grading

More questions from this exam