PMP · Question 23 · Task 7: Plan and manage quality of products/deliverables
A software development project has established quality standards requiring 95% test coverage and zero critical defects before release. During the final sprint, the team discovers they can only achieve 88% test coverage due to time constraints, but there are no critical defects. The release date is fixed due to a marketing campaign. What should the project manager do FIRST?
A software development project has established quality standards requiring 95% test coverage and zero critical defects before release. During the final sprint, the team discovers they can only achieve 88% test coverage due to time constraints, but there are no critical defects. The release date is fixed due to a marketing campaign. What should the project manager do FIRST?
Answer options:
Release the software since there are no critical defects and the marketing campaign cannot be delayed
Delay the release until 95% test coverage is achieved, regardless of the marketing impact
Assess the risk of releasing with 88% coverage and present options to stakeholders for decision
Negotiate with the marketing team to delay the campaign by one week
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
Expert