    PracticePMI PMP®PMI PMP Practice Exam 5Question 24
    Hard1 markMultiple Choice
    Task 8: Plan and manage scoperequirements managementscope managementstakeholder collaborationrequirements prioritization

    PMP · Question 24 · Task 8: Plan and manage scope

    During a project planning session, stakeholders provide conflicting requirements. The sales team wants extensive customization features, the operations team wants standardized processes, and the finance team wants cost minimization. The project scope is becoming unclear due to these competing demands. What should the project manager do FIRST?

    Answer options:

    A.

    Facilitate a requirements prioritization session with all stakeholders to determine business value and trade-offs

    B.

    Document all requirements and let the sponsor decide which ones to include

    C.

    Implement a phased approach where each team gets their requirements in different phases

    D.

    Create three separate project alternatives for stakeholders to choose from

    How to approach this question

    When requirements conflict, facilitate collaborative prioritization to help stakeholders understand trade-offs and make informed decisions about business value.

    Full Answer

    A.Facilitate a requirements prioritization session with all stakeholders to determine business value and trade-offs✓ Correct
    A
    Requirements prioritization sessions help stakeholders understand the business value and trade-offs of competing demands, enabling informed decisions and shared understanding of scope priorities.

    Common mistakes

    Students often choose sponsor decision-making (B) or phased approaches (C), missing the need for collaborative stakeholder prioritization to resolve conflicts and build consensus.
    Question 23All questionsQuestion 25

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →