    PracticePMI PMP®PMI PMP Practice Exam 5Question 25
    Hard1 markMultiple Choice
    Task 9: Integrate project planning activitiesproject integrationdependency managementproject planningtimeline analysis

    PMP · Question 25 · Task 9: Integrate project planning activities

    A project manager is integrating plans from multiple workstreams including development, testing, infrastructure, and training. During the integration analysis, they discover that the testing plan assumes a 2-week testing period, but the development plan shows features being delivered throughout the final month. This creates a dependency gap that could impact the go-live date. What should the project manager do FIRST?

    Answer options:

    A.

    Extend the testing period to accommodate the development delivery schedule

    B.

    Analyze the dependency relationships and assess the impact on the overall project timeline

    C.

    Ask the development team to accelerate their delivery to complete before testing begins

    D.

    Implement parallel testing and development to reduce the overall timeline

    How to approach this question

    When integrating plans reveals dependency gaps, analyze the full impact before making changes to ensure solutions don't create other integration issues.

    Full Answer

    B.Analyze the dependency relationships and assess the impact on the overall project timeline✓ Correct
    B
    Project integration requires understanding all dependency relationships and their impacts before making changes. This prevents solutions that fix one issue but create others.

    Common mistakes

    Students often choose immediate solutions (A, C, or D) without recognizing the need for comprehensive dependency analysis to ensure integration decisions don't create other problems.
    Question 24All questionsQuestion 26

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →