PMP · Question 26 · Task 10: Manage project changes
During project execution, a major technology vendor announces they are discontinuing support for a key software component that the project depends on. This change was not anticipated and will require significant rework to implement an alternative solution. The change will impact scope, schedule, and budget. What should the project manager do FIRST?
Answer options:
Assess the full impact on project objectives and develop response options for stakeholder review
Immediately begin researching alternative software solutions to minimize project delay
Submit a change request to modify the project scope and timeline
Escalate the issue to the sponsor and request guidance on how to proceed
94 questions · hints · full answers · grading