Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned value managementEACCPIcost forecasting

PMP · Question 19 · Task 5: Plan and manage budget and resources

A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>Calculate the Estimate at Completion (EAC) assuming current performance will continue for the remainder of the project. Round to the nearest dollar and enter numbers only.

How to approach this question

Calculate CPI first (EV/AC), then use EAC = BAC/CPI formula. This assumes current cost performance will continue.

Full Answer

When current variances are expected to continue, EAC = BAC/CPI provides the most accurate estimate. CPI = EV/AC = 250,000/280,000 = 0.893. EAC = 500,000/0.893 = 560,000.

Common mistakes

Using wrong EAC formula, calculation errors with CPI, or not rounding to nearest dollar.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam