Hard1 markShort Answer
PMP · Question 19 · Task 5: Plan and manage budget and resources
A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>Calculate the Estimate at Completion (EAC) assuming current performance will continue for the remainder of the project. Round to the nearest dollar and enter numbers only.
A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completion (BAC): $500,000<br/>- Planned Value (PV): $300,000<br/>- Earned Value (EV): $250,000<br/>- Actual Cost (AC): $280,000<br/><br/>Calculate the Estimate at Completion (EAC) assuming current performance will continue for the remainder of the project. Round to the nearest dollar and enter numbers only.
How to approach this question
Calculate CPI first (EV/AC), then use EAC = BAC/CPI formula. This assumes current cost performance will continue.
Full Answer
When current variances are expected to continue, EAC = BAC/CPI provides the most accurate estimate. CPI = EV/AC = 250,000/280,000 = 0.893. EAC = 500,000/0.893 = 560,000.
Common mistakes
Using wrong EAC formula, calculation errors with CPI, or not rounding to nearest dollar.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert