Hard1 markMultiple Choice
Task 2: Lead a teamleadershiphybrid methodologyvision settingstakeholder management

PMP · Question 02 · Task 2: Lead a team

A project manager is leading a hybrid software development project where the client has stable regulatory requirements but wants to see incremental progress every month. The development team is experienced with waterfall but new to agile practices. What should the project manager do FIRST to establish effective leadership?

Answer options:

A.

Implement a pure agile approach since the client wants incremental delivery

B.

Use a traditional waterfall approach since the team is experienced with it

C.

Create a clear vision that combines predictive planning for compliance with iterative delivery for client value

D.

Let the team decide which methodology to use based on their comfort level

How to approach this question

Look for answers that demonstrate setting clear vision and mission while considering all stakeholder needs and constraints. Leadership requires balancing multiple factors.

Full Answer

C.Create a clear vision that combines predictive planning for compliance with iterative delivery for client value✓ Correct
C
Effective project leadership requires setting a clear vision that addresses all stakeholder needs while considering team capabilities and project constraints. This is especially critical in hybrid environments.

Common mistakes

Choosing a one-size-fits-all methodology without considering all factors, or abdicating leadership responsibility to the team without providing direction.