PMP · Question 02 · Task 2: Lead a team
A project manager is leading a hybrid software development project where the client has stable regulatory requirements but wants to see incremental progress every month. The development team is experienced with waterfall but new to agile practices. What should the project manager do FIRST to establish effective leadership?
A project manager is leading a hybrid software development project where the client has stable regulatory requirements but wants to see incremental progress every month. The development team is experienced with waterfall but new to agile practices. What should the project manager do FIRST to establish effective leadership?
Answer options:
Implement a pure agile approach since the client wants incremental delivery
Use a traditional waterfall approach since the team is experienced with it
Create a clear vision that combines predictive planning for compliance with iterative delivery for client value
Let the team decide which methodology to use based on their comfort level