PMP · Question 04 · Task 4: Empower team members and stakeholders
An experienced team member approaches the project manager asking for more autonomy in making technical decisions for their work area. The team member has consistently delivered high-quality work and other team members respect their expertise. What should the project manager do to empower this team member?
An experienced team member approaches the project manager asking for more autonomy in making technical decisions for their work area. The team member has consistently delivered high-quality work and other team members respect their expertise. What should the project manager do to empower this team member?
Answer options:
Maintain current approval processes to ensure consistency across all team members
Define clear boundaries and decision-making authority for their technical area while establishing check-in points
Grant full decision-making authority without any oversight requirements
Ask the team member to document their decision-making process for future reference
How to approach this question
Full Answer
Common mistakes