PMP · Question 06 · Task 6: Build a team
A project manager is forming a new cross-functional team for a complex software integration project. The project requires expertise in legacy systems, modern APIs, database management, and user experience design. What should the project manager do FIRST when building this team?
Answer options:
Request the most senior available resources from each functional area
Form the team with available resources and provide training to fill skill gaps
Analyze the specific technical and functional skills required and map them to available resources
Create a small core team and add specialists as needed during project execution